system was down more than it was up, he says.
Because the system was so unreliable, it was never
embraced by the team, Warcholski adds. Eventually, DC
employees became so disillusioned with the equipment that
many simply bypassed the palletizer and supporting conveyors and sent trucks to regular dock doors for manual
unloading, according to Dave Rebata of Flostor, an integrator that stepped in to help Meyer address the issue.
As for the source of the problem, Warcholski does not blame
the equipment itself. There was nothing wrong with the palletizer’s hardware, he says. Instead, he believes that Meyer
used too many integrators to incorporate the palletizer into
its overall material handling system. This lack of cohesiveness
caused continual failures for the palletizer and kept it from
working smoothly with the company’s conveyor systems.
It was obvious to Warcholski and his team that something
had to be done. The company couldn’t afford to carry what
was essentially a non-performing asset on its books.
Replacement wasn’t an option either—particularly as
Meyer was already in the middle of an AS/RS installation
project at its main DC in Fairfield, Calif., where it was consolidating distribution operations. The team would have to
find a way to make the existing asset work in harmony with
the rest of the equipment—in other words, solve the integration problem.
Coincidentally, Warcholski’s team was already working
with an integrator, Flostor, on another project—one that
involved the installation of a pick module at the Fairfield
DC. It was during a budget meeting with Flostor that a
member of Warcholski’s team had a unique idea: Why not
use the same conveyors and controls that were already being
used to feed the palletizer on the inbound side to move outbound products from the pick module to the correct outbound trailer? In other words, connect the conveyors to the
planned pick module, add a sortation system to the existing
conveyors, and then extend the conveyors into trucks for
outbound delivery. “The more we looked at it, the more we
thought, ‘Yeah, that’s a really good idea,’” recalls Rebata.
FIRST STEP: BRAIN SURGERY
But first, the team needed to get the palletizer to do what it
was designed to do. “We basically had to gut the current system and give it a new brain,” explains Warcholski. “That
doesn’t mean we were disassembling any of the mechanical
pieces. It was really looking into the software and partnering back up with the manufacturer, Columbia, and getting
it working the way it needed to.”
This time around, Meyer was determined not to repeat past
mistakes. “When we [first set up the system], there were too
many people involved,” says Warcholski. “This time, we went
with Flostor and told them, ‘You’re the single integrator.’”
After partnering with Columbia to work out the bugs in
the system, Flostor began looking at the mechanics of incor-
porating the palletizer case conveyor into the outbound
flow. Could the conveyor be easily switched from running in
one direction for inbound receiving to running the opposite
way for outbound deliveries? Was there a way to set up the
system so that Meyer could quickly turn off the palletizer
and turn on the sorter as part of its daily routine?
After studying the problem, the integrator decided the
answer to both questions was yes. Working together with
Meyer, Flostor successfully assembled a pick module that
could interface with the palletizer and be used for outbound
sortation. This was no small accomplishment, according to
Rebata. “It’s very unusual for somebody to come in and do
this using an existing system,” he says. “By the time that system is up and running the way it should be for one process,
it’s very difficult to make it turn on a dime and work for
another process. A lot of work has to go behind it.”
TWO FOR ONE
But it was this decision to use the conveyor system in two
different ways that really made the project a success, according to Warcholski. Not only was Meyer finally able to use
the equipment for its intended purpose, but the company
was also able to use it in a totally different capacity.
By all accounts, the project has resulted in significant
operational benefits. “It increased our volume capacity
twofold, allowed us to reduce labor, and increased our productivity,” says Warcholski. Now, during non-peak season,
the swing shift uses the palletizer on the inbound side, and
the day shift uses it to process outbound cases. This has
allowed the company to reduce its non-peak outbound
shifts from two to one.
Better yet, the solution proved economical. By reusing an
existing system, the company was able to avoid making a $2
million investment in new conveyors and controls. In addition, the implementation time was much shorter than if
Meyer had started from scratch. The company began to see
a payback immediately, according to Warcholski.
Meyer is not done with reviewing its palletizer and conveyor system (or for that matter, the other systems that were
installed around it). Based on the success of the project, the
company says that over the next three to five years, it will be
continually looking at its systems to make sure they’re performing at optimal levels—and being put to maximum use. ;