At best, its analysis showed, by taking on an adjacent site at
one of the facilities and installing a bulk automated storage
and retrieval system (AS/RS), the existing operations could
provide just under 30,000 pallet positions—far
short of expected requirements. Further, adapting
the existing facilities would not provide the flexible order picking systems needed. That led to the
decision to explore construction of a greenfield
facility—and building the business case to persuade
UTi’s board that the investment made sense.
As for how big the new facility would be, the initial
design concept indicated that a 50,000-square-me-
ter (538,195-square-foot) building would meet
UTi’s needs. In late 2009, the company began
soliciting proposals from construction firms for the
building and proposals from three major material
handling equipment manufacturers it had worked
with in the past for the equipment.
Van Rensburg emphasizes that UTi left it up
to the equipment manufacturers to suggest what
specific technology would work best. The initial
design proposals came back in April 2010. Those propos-
als provided UTi with options that varied from a very-
narrow-aisle operation to a wide-aisle concept to an AS/
RS-centric operation. The AS/RS proposal had the lowest
staff requirements of the three, would limit access to stock
(important for security reasons), could be operated with
the lights out in much of the building, and was overall, the
lowest-cost solution, and that’s what the company
selected. The final design included a large bulk AS/
RS, a cross-belt sorter, and other technologies.
The property developer broke ground in May
2011, and the facility began operations in October
2012. The old facilities were completely closed by
February 2013. One key requirement in the process
of shifting operations was to minimize disruption
to daily activities. “That was quite interesting and
quite stressful,” van Rensburg says. “We distribute
around 55 percent of all pharmaceuticals in South
Africa. We could not disrupt the market.” But in
the end, the process worked. While there were some
disruptions, he says, they were not significant.
Construction delays, though, did lead to one
problem that in retrospect, the managers would
have handled differently. Adrienne Youell, one of
the UTi managers who led the project, explains
that the original plan provided for three months of testing
before opening the facility. But the construction delays cut
into that time. And failure to vacate the facilities the com-
pany was leaving would have been costly. That forced UTi
AISC CERTIFIED SYSTEMS
Cubic Designs is the only mezzanine
manufacturer certified by the American
Institute of Steel Construction (AISC).
NO CHARGE, PE STAMPED DRAWINGS
Our PE stamped drawings are the mark
your facility should depend upon when it
comes to mezzanine safety and strength.
You can’t take chances when it comes to safety in
your facility. So, why compromise?
As the mezzanine authority, Cubic Designs offers the
professionally-engineered, AISC-certified systems
that deliver the security, strength and durability you
need to safely maximize your existing space.
• Designed for structural integrity
• Engineered for all seismic zones
• Manufactured with high-quality steel
• In-house team of professional engineers
Choose the mezzanine manufacturer that won’t
let you down. Call Cubic Designs.
the perfect fit
THE
MEZZANINE
AUTHORITY
VISIT US AT WERC. BOOTH #1206